Over the last few months, Mirvac has been working closely with our contractor to develop a programme that would help minimise the impact of these works to neighbouring residents whilst maintaining compliance with RMS approval.

This includes the implementation of respite periods in between each stage of work (as opposed to a continuation of each stage one after the other) to ensure that sufficient break is provided to residents.

As such works will be carried out across the following three periods:

  • Stage 1 (13th September – 20th October): Works to be carried out between 5:00pm – 9:00pm, Monday to Wednesdays.
  • Stage 2 (Late November – pre-Christmas): Works to be carried out between 8:00pm – 5:00am across a maximum of 3 nights per week.
  • Stage 3 (mid-January to mid-February): Works to be carried out between 8:00pm – 5:00am across a maximum of 3 nights per week.

To help minimise the overall impact of the works the Stage 1 works will see high impact noisy works cease by 5:00pm and for the Stage 2 and 3 works, high impact noisy works will be limited 8:00pm – 12:00am, with non-high impact noisy works scheduled between 12:00am – 5:00am.
 
We will be issuing the attached notification the adjacent residents today and in recognition of the impact on local traffic networks, we would appreciate your assistance in communicating information about the works to your respective members.
 
Please let me know if you required any further information.
 